A purchase order is a commitment approved before the money is spent. Raised after the invoice, it is just paperwork.
A purchase order process runs from requisition to approval, PO issue, goods receipt, invoice and three-way match, then payment. The control value comes from approving spend before it is committed. Set clear rules on what needs a PO, who approves at each amount, and what happens to invoices that arrive without one.
Write a short policy that answers three questions:
A PO raised after the invoice is dated gives none of the control benefit. With PO date in column C and invoice date in column D of your invoice register:
=IF(AND(C2<>"",D2<>"",C2>D2),"Retro PO","")
Pivot the flagged rows by requester and by supplier. A few names usually account for most of them, and a conversation fixes more than a new rule.
A PO process that is slow gets bypassed. Keep approval routes short, let budget holders approve on a phone, and set up blanket POs for frequent low-value purchases from the same supplier. Report PO compliance monthly: the share of eligible spend that had a PO before the invoice date.
The process is the same in the UK and US. UK teams may say "purchase requisition" and "goods received note (GRN)"; US teams often say "receiving report". Prices on POs should state whether they include VAT or sales tax.
Supplier statement to AP ledger. Finds invoices you haven't posted, credit notes still to come, price differences, duplicate postings and payments in transit, and builds the supplier reconciliation. Runs in your browser on your own computer: nothing is uploaded.
Paste your invoice list and see likely duplicates in minutes. Free Excel file: enter your work email to download it.
The Accounts Payable Control System runs four duplicate-invoice tests, supplier master fraud checks and a three-way match on every invoice, with a payment run release gate that blocks release while exceptions are open. Excel, no macros, one-time price.
Requisition, approval, PO issued to an approved supplier, goods receipt, invoice, three-way match, then payment on the due date.
A PO raised after the goods were ordered or the invoice arrived. It records the spend but gives none of the control benefit of approving it in advance.
Usually not. Most organisations exempt a short, written list of categories such as utilities, rent and taxes. Everything else above a set amount should have a PO before the spend is committed.
Last updated 21 October 2026. General guidance for finance teams; check it against your own policies, systems and local rules.